Preparatory works and building demolition.

Grainger plc appointed General Demolition Limited to carry out the demolition works. In the coming months, the appointment of a main contractor will be confirmed.

Ahead of this first phase of work, we would like to reassure residents and site neighbours that

extensive measures have been put in place to ensure disruption will be minimised.

A detailed Demolition Management Plan has been developed by Grainger and the General Demolition

Ltd that sets out the strict guidelines in which the works will be carried out.

We would like to thank our neighbours for their patience and tolerance during these necessary works which will run from mid-April for approximately twelve weeks at the following times :

  • Monday to Friday – 8am to 6pm
  • Saturday – 8am to 1pm
  • Sunday and Bank Holidays: No works without prior approval from Haringey Council